Hi,
We have 4 node NLB cluster in Production site and we are planning protect it with SRM 5.1.1.
SRM 5.1.1 supports 2 Microsoft Cluster Server (MSCS) nodes. vSphere 5.1.x supports up to 5 MSCS nodes. SRM 5.1.x supports 2 MSCS nodes.
Is it possible to have 4 node NLB in production and protect only two nodes with SRM? as we just need two nodes for DR.