Hello.
Product:
vRealize automation version 7.2.0 (build 4659752).
Problem:
I request a deployment with machine with "Lease days = 90". After 1 month of using it, I want to change lease to 1 year, but can't do it in one step (change date from 1.1.2017 to 1.1.2018)
Workaround: I need change lease 4 times (1.1.2017 -> 1.4.2017 -> 1.7.2017 -> 1.11. 2017 -> 1.1.2018)
4 steps, because 90 days period is a default lease date for this deployment.
On previous deployed vRa Automation, I didn't have these problems, I could change lease to any period.
Could you answer me, this is "bug" or "feature" of vRa 7.2 ?