Hi,
I am looking to understand if SRM 6.5.x supports Platform Services Controller High Availability (PSC HA)? (VMware Knowledge Base)
I am deploying vCenter Server High Availability (VCHA) clusters with PSC HA using F5 LTM Load Balancers, but I am not 100% sure if SRM supports it?
I have attached a block diagram of my proposed final setup. There will be two VCHA clusters and two PSC's per SSO site, with 2 sites in the SSO domain. All vCenter Servers will be federated using Enhanced Linked Mode (ELM). Only 1 VCHA cluster in each SSO site will be using SRM to protect/recover it's workloads.
All vCenters & PSC's will be running version 6.5 update 1.
The PSC's will been deployed in sequence 1->2->3->4 and a final manual PSC replication agreement will be created between PSC 4 and PSC 1, to create a ring topology.
If I cannot use PSC HA with SRM:
- can I still use it for the workload VCHA cluster?
- which PSC's should I directly configure SRM to use?
Any advice or gotchas you can point out will be appreciated.
Cheers,